Location: Albany, Georgia

Client: Marine Corps Logistics Base

Project Description: LRA provided design/build services for the construction of a 100’ x 100’ x 22’ high pre-engineered building, a 30’ x 10’ x 28’ enclosed pre-engineered building cover for conveyor operated oven & paint booths, a 8” concrete factory floor, two fast action rollup doors with sensors, a 4” compressed air loop, hose bibbs @ 20’ on center, two fork lift ramps, and 4 ft high 8 inch thick concrete foundation walls. Included in the construction were two 220’ long, 12 ft per minute I-beam conveyor lines for two paint booths. The booths have two 450 degree curing ovens, an 800 amp motor control center, a fire alarm system, fire protective sprinklers, a 750 KVA transformer, two 45,000 CFM make up air units and four variable speed exhaust fans.